Which of the following is a primary responsibility of the architect during construction observation?
According to ATA Document C401, Architect-Consultant Agreement, clearances and tolerances required by the mechanical work relative to the structural system are coordinated through which one of the following parties?
In response to a request for qualifications for a prospective project, the architect assembles a project team of mechanical, electrical, plumbing, and fire protection engineers.
What is the project?
While conducting a site visit for a residential tower delivered through the design-build method, an architect observes several construction workers without hard hats and other unsafe working conditions.
How should the architect proceed?
Evaluation and mitigation of indoor air quality in an existing facility assessment would include participation by which of the following? Check the three that apply.
An architecture firm has a C401 agreement with their consultants for a new design-bid-build residential tower.
The architect has approved a schedule provided by the mechanical engineer that includes a two-week quality control review after each delivery milestone.
During the design development phase, the owner requests that the architect change the 8,000-square-foot business center amenity for tenants to a private restaurant. The mechanical engineer informs the architect that their schedule must be extended by four weeks to meet the owner's request.
What should the architecture firm do first to maintain the start of construction?
An architecture firm is negotiating a contract with an owner for a $2,000,000 project. The proposed architectural-only fee is 5% of the cost of construction through the end of the Construction Document Phase.
During the negotiations, the owner wants to apply for a building permit in 7 weeks without exceeding the original budget constraints. The project staff currently consists of 2 people who have an hourly rate of $100.
What is the minimum project staff required to meet the owner's new schedule?
According to ATA owner-architect agreements, who is responsible for the cost of evaluating significant substitutions proposed by the contractor, subcontractors, or suppliers and the cost of making subsequent revisions to drawings, specifications, and other documentation?