Your customer plans to use Oracle Representational State Transfer (REST) API with Oracle Supply Chain Management Cloud (Oracle SCM Cloud) to support integration requirements.
Identify four REST resources and thecorresponding HTTP action available with Manufacturing Cloud.
Your customer has multiple distribution centers and a few manufacturing plants. Plants make different items with some overlap between them in terms of productsmanufactured. The distribution centers stock parts from all plants. A Corporate Engineering team is responsible for centrally defining items and catalogues. This team defines the items and sets the attributes for most parameters. The respective distribution centers and manufacturing plants are allowed to change some attributes locally.
Identify two different ways of achieving this requirement.
During a Manufacturing Cloud implementation, the Production Supervisor wants to close thework orders for last month and wants to make sure that the work orders include the correct cost.
Identify the approach to be taken by the Production Supervisor.
Which two steps should you use to create a new Oracle Transactional Business Intelligence report in the ManufacturingCloud?
A plant operates three continuous daily shifts of eight hours each for five days in a week. One unit of the resource R1 within the plant is assigned for two shifts to work area W1. On a particular day in a given week, due to unscheduled maintenance thatneeded to be performed on the resource R1, it was not available for two hours during each of the assigned shifts.
Determine the available capacity of the resource R1 for thatweek.
The Cost Accountant has reported to the Production Supervisor that the Work Order transactions are not getting transferred to Costing.
Identify the reason for work order transactions not getting transferred to Costing.
In a manufacturing plant, two purchase components P1 and P2 and a resource R1 are required to assemble a product. The cost of the assembly is calculated by using thestandard costing method. The work definition and resource rates of the assembly have been defined as required.
A cost accountant is estimating cost of the assembly, analyzing rolled-up costs before finally publishing estimates as frozen standards to cost accounting by using a cost planning scenario. While reviewing rolled up costs, the extended costs of purchase components are not included in a rolled-up scenario.