최신SAP Certified Application Associate - Production Planning & Manufacturing with SAP ERP 6.0 EHP7 - C_TSCM42_67무료샘플문제
Which activity can trigger an automatic availability check for the components of a production order?
When analyzing the SAP ECC order report for a planned order for a finished product, you discover that one of the assemblies will not be available in time for the scheduled final assembly because of automatic forward scheduling.
Which planning procedure do you use to create a feasible production plan from a requirements planning perspective?
You have maintained planning strategy group 10 (make-to-stock production) in the material master (SAP ECC) of a material. For the coming months, you have planned requirements with requirement type LSF (derived from main strategy 10). Now, you want to change the requirement type from LSF to VSF (in accordance with planning strategy 40, planning with final assembly) for requirements in the existing production plan.
Which of the following scenarios are applicable in this case? (Choose two)
When testing requirements planning in plant 1000, you receive the error message displayed below. Large numbers of materials are already available in plant 1000. As a first step in solving the problem, you activate requirements planning in the Customizing for plant 1000.

What further tasks do you perform before you can use requirements planning in plant 1000 in SAP ECC?
What do you have to consider regarding lot size procedures?
In your company planning strategies are used in the SAP-ECC demand management that are based on consumption. Which of the following statements about consumption is true?
(Choose two.)
In SAP ECC, you calculate the standard available capacity for a work center capacity using the following data:
- Start: 7:00:00 a.m.
- End: 3:00:00 p.m.
- Break duration: 1 hour
- Rate of utilization: 80%
- Overload: 110%
- Number of individual capacities: 1
How large is the standard available capacity?
In what sequence are the steps of material requirements planning performed in SAP ECC?
The stock/requirements list for a finished product contains only one sales order and one fixed planned order with the same quantity. The availability dates for both MRP elements are on working days. The availability date for the fixed planned order is set to a later date than the one for the sales order.
However, a corresponding rescheduling exception message does not appear.
What could be the reasons? (Choose two)