Handling of warranty returns, process improvement team meetings and rework to meet customer expectations are all examples of business costs that are classified as ________________ .
SPC Charts are used extensively in different business and decision-making environments. In this example a vendor is being selected based on speed of delivery. Which of the conclusions would help you pick a vendor for your needs regarding lead-time of delivery from your vendors? (Note: There are 4 correct answers).
Early in a project a Belt will want to begin to identify and evaluate risk factors for the subject process and will therefore begin building a(n) ______________.
A valid Multiple Linear Regression (MLR) is characterized by all of these except _______________________.
Time is always the metric on the horizontal scale of a(n) ___________ Chart.
If in an experiment all possible variable pairs sum to zero the design is Orthogonal.
The Central Limit Theorem says that as the sample size becomes large the sample Mean distribution will form a Normal Distribution, ____________________.
When a Belt implements an improvement that is automated thus requiring no particular understanding for use he has applied which Lean tool?
Kanban establishes a means of monitoring production, conveyance and delivery information such that efficient flow is established. The method used by Kanban is to require a _________ before anything moves.
Calculate the Rolled Throughput Yield of this process using this data.
DatA. unit input: 1450, unit output: 1390, defects repaireD. 320, scrap: 60
One of the foundations of Lean Six Sigma is the concept that the output of a process (Y) is influenced by the process inputs (X's) and is commonly shown as which formula?