최신PECB ISO 21502 Lead Project Manager - ISO-21502-Lead-Project-Manager무료샘플문제

문제1
What should the project manager collect and analyze, among others, to assess the progress of the project?

정답: C
설명: (ITDumpsKR 회원만 볼 수 있음)
문제2
Scenario:
Leute is a low-cost airline, headquartered in Wien, Austria. The company aims to offer passengers optimal options regarding its services and gain the lead role among other competitors in the airline industry. Recently, Leute experienced a major drop in revenue due to negative reviews from customers in various online platforms. To increase its profit and enhance customer satisfaction, the company decided to expand its in- flight services by offering entertainment, such as movies, audio books, and games, food for purchase in economy and full meals in premium cabins, and comforts, such as blankets and pillows. For the implementation of this project and future projects of the airline, the CEO of Leute, Michaele Wagner, decided to follow the guidelines of ISO 21502 on project management.
Initially, Allison, the project manager, created a short document in which she justified and summarized all project aspects, including: the nature and purpose of the project, the objectives of the project, key milestones of the project and the time needed to complete the project, and the audience that the project targets.
Afterward, Allison held a meeting with Michaele during which she presented this document and briefly explained each of its points. After a considerable amount of analysis and discussions, the project initiation was approved by Michaele. In addition, a team of eighteen members was authorized to start with the project activities.
While undertaking the project activities, Allison ensured that each work package takes longer than 8 hours, but less than 80 hours, so that they would be completed in 1 to 10 working days. In addition, during this phase, several changes were made in the predefined aspects of the project, which were approved by Nick Todd, the project sponsor. For instance, initially, the project delivery was set to be completed after six months. However, considering how the project was implemented and the time required for the completion of each phase, the deadline for the project completion was postponed for another two months. These changes were also reflected in the business case, which was updated accordingly.
A month after the project execution began, Allison conducted an earned value analysis to measure the progress of the project up to that stage. She measured how efficiently the work was being performed with regard to its budgeted cost, after which she concluded that it was going according to the plan. Moreover, she organized a meeting with relevant project stakeholders in order to communicate the progress report to them.
Question:
Allison prepared a short document in which she justified and summarized all project aspects. Which of the following did Allison create in this case?

정답: C
설명: (ITDumpsKR 회원만 볼 수 있음)
문제3
Scenario:
Exhibix is a video game developer headquartered in Zagreb, Croatia, which is known for producing therapeutic video games for children dealing with ADHD. In order to improve users' experience, Exhibix suggested undertaking a project that would enable users to interact with the virtual content in the form of holograms through augmented reality glasses in the video games. For this project, the management decided to follow the guidelines of ISO 21502 on project management.
Prior to formalizing project management, the management of Exhibix assessed, among others, the potential impacts that the project management approach may have on both internal and external stakeholders. In addition, they determined if there were sufficient resources, both human and financial, for the formalized project management. Furthermore, during this period, the management decided to assess only the nature of previous projects, due to their successful delivery.
After formalizing project management, the project board organized a meeting during which they delegated their responsibilities to the project sponsor. Following this meeting, the project sponsor and project manager proceeded to define the project phases and their time frames. Considering the complexity of the project, the project manager suggested leaving open the possibility of overlapping certain phases of the project.
The preparations began in June, and the project manager and the team, consisting of 20 highly skilled professionals, had approximately six months to implement the project. During the implementation of the project, the project team noticed that the low maturity level of the company's project management and the limited availability of resources were likely to have a negative impact on the performance of the project. With the deadline approaching, the team was also under a lot of pressure to close the project on time.
They were confronted with numerous challenges with the AR software, which led to the extension of the deadline for the project completion. During this period, the project office assisted the project manager and the team by providing administrative support and managing information regarding the project. Following these events, the project manager and the team were able to complete the project within the new set deadline. After the project sponsor confirmed the project closure, the AR glasses were released for use.
Question:
Based on the fourth paragraph of scenario 2, what factors did the project team notice that were likely to have a detrimental impact on the project's performance?

정답: C
설명: (ITDumpsKR 회원만 볼 수 있음)
문제4
Scenario:
Mallebare is an American company which designs and manufactures gaming accessories. Apart from keyboards, mice, and controllers, the company also manufactures high-quality headsets for which it is widely known. Recently, upon the request of numerous gamers, the company decided to manufacture mousepads too.
For this project, Luke, the CEO of the company, assigned Ross, a senior designer of the company, as the project manager, whereas Smith, a senior engineer, was assigned as project sponsor. In addition, Luke stated the project should be complete within three months, as the company is aiming to promote the mousepads in a major gaming tournament. Lastly, Luke required them to utilize the guidelines of ISO 21502 to manage the project.
Initially, Ross mobilized the team and held a meeting with them to discuss and develop the project plan. He asked the team members to ensure that major functional aspects of the project are covered in the project plan and to identify any issue that might arise throughout the project life cycle. Ross explained that this request comes as a result of the tight deadline of the project and the team must develop a concise plan. Ross added that the plan will not be changed in any circumstance and will be followed in detail.
Following that, Ross and the team discussed the engagement of all relevant stakeholders throughout the project. Ross used a power/interest matrix to categorize all stakeholders in four different groups, where the tournament organizers were categorized as stakeholders with low interest but high power in the project. On the other hand, end users, the gamers, were categorized as stakeholders with high interest and high power in the project, so the project team created a survey to determine their needs and requirements.
Moreover, Ross was aware of the importance of effective communication for the success of the project.
Therefore, he developed a communication plan which would ensure that each individual involved in the project gets the right information in a timely manner. The plan indicated that ad hoc discussions would be conducted in more complex and personal cases, whereas notes and text messages would be used for transmitting simple and factual information. Ross claimed that this model had been successful in previous projects conducted by the company because it allows faster processing of information and includes natural use of language. In addition, Ross determined that a relationship among project team members needs to be established to ensure productive work.
Question:
According to scenario 6, the communication plan indicated that ad hoc discussions would be conducted in more complex and personal cases, whereas notes and text messages would be used for transmitting simple and factual information. What type(s) of communication are planned in this case?

정답: A
설명: (ITDumpsKR 회원만 볼 수 있음)
문제5
Which of the following statements is the definition of project interface?

정답: B
설명: (ITDumpsKR 회원만 볼 수 있음)
문제6
Arka, a manufacturing company, has initiated a project together with two other companies. Jim, who is the CEO of Arka, has suggested that the project board consist of representatives from each company instead of only Arka's personnel in order to increase transparency. However, the representatives of the other companies disagreed, claiming that this would not be compliant with ISO 21502 guidelines. Instead, they are suggesting that they outsource the function of the project board to avoid conflicts of interest. Is this in compliance with ISO 21502?

정답: B
설명: (ITDumpsKR 회원만 볼 수 있음)
문제7
Scenario:
Mallebare is an American company which designs and manufactures gaming accessories. Apart from keyboards, mice, and controllers, the company also manufactures high-quality headsets for which it is widely known. Recently, upon the request of numerous gamers, the company decided to manufacture mousepads too.
For this project, Luke, the CEO of the company, assigned Ross, a senior designer of the company, as the project manager, whereas Smith, a senior engineer, was assigned as project sponsor. In addition, Luke stated the project should be complete within three months, as the company is aiming to promote the mousepads in a major gaming tournament. Lastly, Luke required them to utilize the guidelines of ISO 21502 to manage the project.
Initially, Ross mobilized the team and held a meeting with them to discuss and develop the project plan. He asked the team members to ensure that major functional aspects of the project are covered in the project plan and to identify any issue that might arise throughout the project life cycle. Ross explained that this request comes as a result of the tight deadline of the project and the team must develop a concise plan. Ross added that the plan will not be changed in any circumstance and will be followed in detail.
Following that, Ross and the team discussed the engagement of all relevant stakeholders throughout the project. Ross used a power/interest matrix to categorize all stakeholders in four different groups, where the tournament organizers were categorized as stakeholders with low interest but high power in the project. On the other hand, end users, the gamers, were categorized as stakeholders with high interest and high power in the project, so the project team created a survey to determine their needs and requirements.
Moreover, Ross was aware of the importance of effective communication for the success of the project.
Therefore, he developed a communication plan which would ensure that each individual involved in the project gets the right information in a timely manner. The plan indicated that ad hoc discussions would be conducted in more complex and personal cases, whereas notes and text messages would be used for transmitting simple and factual information. Ross claimed that this model had been successful in previous projects conducted by the company because it allows faster processing of information and includes natural use of language. In addition, Ross determined that a relationship among project team members needs to be established to ensure productive work.
Question:
Ross required the team to develop a concise plan which will be followed in detail and that will not be changed in any circumstance. Is this compliant with ISO 21502?

정답: B
설명: (ITDumpsKR 회원만 볼 수 있음)
문제8
Scenario:
Leute is a low-cost airline, headquartered in Wien, Austria. The company aims to offer passengers optimal options regarding its services and gain the lead role among other competitors in the airline industry. Recently, Leute experienced a major drop in revenue due to negative reviews from customers in various online platforms. To increase its profit and enhance customer satisfaction, the company decided to expand its in- flight services by offering entertainment, such as movies, audio books, and games, food for purchase in economy and full meals in premium cabins, and comforts, such as blankets and pillows. For the implementation of this project and future projects of the airline, the CEO of Leute, Michaele Wagner, decided to follow the guidelines of ISO 21502 on project management.
Initially, Allison, the project manager, created a short document in which she justified and summarized all project aspects, including: the nature and purpose of the project, the objectives of the project, key milestones of the project and the time needed to complete the project, and the audience that the project targets.
Afterward, Allison held a meeting with Michaele during which she presented this document and briefly explained each of its points. After a considerable amount of analysis and discussions, the project initiation was approved by Michaele. In addition, a team of eighteen members was authorized to start with the project activities.
While undertaking the project activities, Allison ensured that each work package takes longer than 8 hours, but less than 80 hours, so that they would be completed in 1 to 10 working days. In addition, during this phase, several changes were made in the predefined aspects of the project, which were approved by Nick Todd, the project sponsor. For instance, initially, the project delivery was set to be completed after six months. However, considering how the project was implemented and the time required for the completion of each phase, the deadline for the project completion was postponed for another two months. These changes were also reflected in the business case, which was updated accordingly.
A month after the project execution began, Allison conducted an earned value analysis to measure the progress of the project up to that stage. She measured how efficiently the work was being performed with regard to its budgeted cost, after which she concluded that it was going according to the plan. Moreover, she organized a meeting with relevant project stakeholders in order to communicate the progress report to them.
Question:
Based on scenario 3, Allison conducted the earned value analysis to measure the efficiency of work being performed with regard to its budgeted cost. Which of the following metrics did Allison use in this case?

정답: C
설명: (ITDumpsKR 회원만 볼 수 있음)
문제9
Scenario:
Tricko is a clothing manufacturer headquartered in Milano, Italy. The company was founded in 2010 by Mario, a famous Italian fashion designer. Over the last few years, the company has seen immense growth and now has a chain of stores across multiple European cities. Following industry trends, the top management of Tricko concluded that the company should establish an online store. As such, they required Lily, an experienced IT engineer, to develop a brief for this potential project. After several meetings and discussions, the top management approved the project brief and assigned Lily as the project manager. For this project, she was instructed to use the guidelines of ISO 21502 on project management.
Lily initiated the project by mobilizing the project team, which included four web developers, two network engineers, and one systems analyst. In order to ensure that every team member is fully aware of their roles and responsibilities, Lily developed team performance domains which would link each project activity with the individuals responsible for undertaking it. She explained to the team members that it is important to clearly understand their roles and responsibilities, considering that the team composition cannot be reassessed or revised once the project plan is authorized to be executed. In addition, Lily defined in a document the project's contribution to the overall objectives of Tricko, which reflected the relevant project requirements and their associated acceptance criteria.
Following that, Lily worked with the project team to discuss project costs. She suggested the team initially establish cost estimates only for the first phase of the project and then for the entire project. In addition, she required cost estimates to be expressed in currency valuations and in labor hours. One of the network engineers suggested that each team member should provide an estimate, and then the team should reach an agreement for a joint estimate. On the other hand, one of the developers suggested establishing an estimate for the costs after the closure of the project, such as advertising and promotion costs. Lily agreed with their suggestions and asked them to provide a total estimate as soon as possible.
Based on the total estimate provided by the project team, Lily developed the project budget and created a list of project activities, divided them into smaller items, and assigned a budget for each item.
Question:
According to scenario 5, Lily defined the project budget by creating a list of project activities, dividing them into smaller items, and assigning a budget for each item. Which method did Lily use to define the project budget?

정답: A
설명: (ITDumpsKR 회원만 볼 수 있음)

자격증의 중요성:

ITDumpsKR 경쟁율이 심한 IT시대에 인증시험을 패스함으로 IT업계 관련 직종에 종사하고자 하는 분들에게는 아주 큰 가산점이 될수 있고 자신만의 위치를 보장할수 있으며 더욱이는 한층 업된 삶을 누릴수 있을수도 있습니다.

ITDumpsKR 제품의 가치:

ITDumpsKR에는 IT인증시험의 최신 학습가이드가 있습니다. ITDumpsKR의 IT전문가들이 자신만의 경험과 끊임없는 노력으로 최고의 학습자료를 작성해 여러분들이 시험에서 패스하도록 도와드립니다.

무료샘플 받아보기:

관심있는 인증시험과목 덤프의 무료샘플을 원하신다면 덤프구매사이트의 PDF Version Demo 버튼을 클릭하고 메일주소를 입력하시면 바로 다운받아 덤프의 일부분 문제를 체험해 보실수 있습니다.

완벽한 서비스 제공:

ITDumpsKR는 한국어로 온라인상담과 메일상담을 받습니다. 덤프구매후 일년동안 무료 업데이트 서비스를 제공해드리며 구매일로 부터 60일내에 시험에서 떨어지는 경우 덤프비용 전액을 환불해드려 고객님의 부담을 덜어드립니다.