최신PRINCE2 Project Management Practitioner (Version 7) - PRINCE2-7-Practitioner무료샘플문제

문제1
RISK
Here are three items of information relating to the 'risk' practice.
In which management product (A-E) should each item be recorded?
Choose only ONE management product for each item of information. Each management product may be used once, more than once, or not at all.

정답: A,C
설명: (ITDumpsKR 회원만 볼 수 있음)
문제2
During a periodic evaluation of the security-system work package, the team manager reviews the work package description, team plan, and the related issue, risk, quality, product, and lessons information. Missing electrical cabling means that installation is now forecast to finish one week late, exceeding the work-package time tolerance.
The team manager raises the issue with the project manager and reports the current status in the checkpoint report. Is this an appropriate application of the 'evaluate a work package' activity, and why?

정답: C
설명: (ITDumpsKR 회원만 볼 수 있음)
문제3
During initiation, the project executive asks the project manager to evaluate a credible business option that omits the underground car park. The project manager includes an investment appraisal of that option in the full business case, despite the main contractor's objection.
Is this an appropriate application of the business case practice, and why?

정답: A
설명: (ITDumpsKR 회원만 볼 수 있음)
문제4
ISSUES
During stage 1, BuildyBrick was appointed by the procurement team manager as the main contractor for the project. The project is now in stage 3 and BuildyBrick is part way through the site preparation. Following an environmental survey report, BuildyBrick will have to delay the site clearance by several weeks to enable protected amphibians to be relocated. There are two options to deal with this issue. The first is to wait for BuildyBrick to clear the site, but this will take longer. The second is to hire an additional contractor to clear the site more quickly, but this will cost more. Both of these options can be completed within cost and time tolerances, but appointing an additional contractor is beyond the project manager's delegated authority.
Here are three actions related to the resolution of this issue.
Which role (A-E) should be responsible for each action?
Choose only ONE role for each action. Each role can be used once, more than once, or not at all.

정답: B,C,E
설명: (ITDumpsKR 회원만 볼 수 있음)
문제5
A high-level requirement that the design should be consistent with its surroundings was recorded during
'starting up a project'. During initiation, the project manager works with Council members, residents, retailers and BuildyBrick to clarify the required design characteristics and define measurable acceptance criteria.
Which management product should be updated with this information?

정답: D
설명: (ITDumpsKR 회원만 볼 수 있음)
문제6
The LouisShopping project is part of the LOB portfolio and is now in the 'initiating a project' process. The project manager asks the portfolio office to support preparation of the digital and data management approach.
Why is this involvement appropriate during the 'agree the management approaches' activity?

정답: B
설명: (ITDumpsKR 회원만 볼 수 있음)

자격증의 중요성:

ITDumpsKR 경쟁율이 심한 IT시대에 인증시험을 패스함으로 IT업계 관련 직종에 종사하고자 하는 분들에게는 아주 큰 가산점이 될수 있고 자신만의 위치를 보장할수 있으며 더욱이는 한층 업된 삶을 누릴수 있을수도 있습니다.

ITDumpsKR 제품의 가치:

ITDumpsKR에는 IT인증시험의 최신 학습가이드가 있습니다. ITDumpsKR의 IT전문가들이 자신만의 경험과 끊임없는 노력으로 최고의 학습자료를 작성해 여러분들이 시험에서 패스하도록 도와드립니다.

무료샘플 받아보기:

관심있는 인증시험과목 덤프의 무료샘플을 원하신다면 덤프구매사이트의 PDF Version Demo 버튼을 클릭하고 메일주소를 입력하시면 바로 다운받아 덤프의 일부분 문제를 체험해 보실수 있습니다.

완벽한 서비스 제공:

ITDumpsKR는 한국어로 온라인상담과 메일상담을 받습니다. 덤프구매후 일년동안 무료 업데이트 서비스를 제공해드리며 구매일로 부터 60일내에 시험에서 떨어지는 경우 덤프비용 전액을 환불해드려 고객님의 부담을 덜어드립니다.