RISK
Here are three items of information relating to the 'risk' practice.
In which management product (A-E) should each item be recorded?
Choose only ONE management product for each item of information. Each management product may be used once, more than once, or not at all.
During a periodic evaluation of the security-system work package, the team manager reviews the work package description, team plan, and the related issue, risk, quality, product, and lessons information. Missing electrical cabling means that installation is now forecast to finish one week late, exceeding the work-package time tolerance.
The team manager raises the issue with the project manager and reports the current status in the checkpoint report. Is this an appropriate application of the 'evaluate a work package' activity, and why?
During initiation, the project executive asks the project manager to evaluate a credible business option that omits the underground car park. The project manager includes an investment appraisal of that option in the full business case, despite the main contractor's objection.
Is this an appropriate application of the business case practice, and why?
ISSUES
During stage 1, BuildyBrick was appointed by the procurement team manager as the main contractor for the project. The project is now in stage 3 and BuildyBrick is part way through the site preparation. Following an environmental survey report, BuildyBrick will have to delay the site clearance by several weeks to enable protected amphibians to be relocated. There are two options to deal with this issue. The first is to wait for BuildyBrick to clear the site, but this will take longer. The second is to hire an additional contractor to clear the site more quickly, but this will cost more. Both of these options can be completed within cost and time tolerances, but appointing an additional contractor is beyond the project manager's delegated authority.
Here are three actions related to the resolution of this issue.
Which role (A-E) should be responsible for each action?
Choose only ONE role for each action. Each role can be used once, more than once, or not at all.
A high-level requirement that the design should be consistent with its surroundings was recorded during
'starting up a project'. During initiation, the project manager works with Council members, residents, retailers and BuildyBrick to clarify the required design characteristics and define measurable acceptance criteria.
Which management product should be updated with this information?
The LouisShopping project is part of the LOB portfolio and is now in the 'initiating a project' process. The project manager asks the portfolio office to support preparation of the digital and data management approach.
Why is this involvement appropriate during the 'agree the management approaches' activity?